CURRENT ON GOING PROJECTS :

 

CURRENT ON GOING PROJECTS

S.NO.

NAME OF PROJECTS

TYPE/NATURE

PROGRESS

COMPLETION TIME

01

ZUARA DESALINATION PLANT

CIVIL WORK

81%

30/8/05

02

ABUTARABA DESALINATION PLANT

CIVIL WORK

5%

1/11/06

03

ABUTARABA 66 KV S/S

CIVIL WORK

35%

1/3/06

04

CABLE 275 KV . B.N TO B.C

245KV CABLE

10%

31/12/05

05

OHTL , MARADA –BISHR

66 KV T.L.

50%

31/12/05

06

BUHIDIMA 33KV S/S

CIVIL WORK

90%

30/6/05

07

NAY ELSALAM 33 KV S/S

CIVIL WORK

90%

30/6/05

08

RUESAAT 33KV S/S

CIVIL WORK

90%

30/6/05

09

ABUTARABA HOUSING

CIVIL WORK

5%

1/6/07

10

TARHUNA AGRI.PROJ. ELECTRIFICATION

ELECT & CIVIL

45%

1/12/05

11

ABUNGAIM OHTL

66 KV T.L

5%

30/8/05

12

AGEDABIA 33KV S/S

CIVIL WORK

10%

1/6/06

13

11 KV S/S

CIVIL WORK

95%

30/8/05

14

ADMINS. BUILDING

CIVIL WORK

75%

30/12/05

15

HIGH MAST FOR ILLUMINATION AT SIRT

CIVIL WORK/ ELECT. WORK

65%

15/7/05

16

33 KV OHTL

OHTL

UNDER ERECTION